We surveyed those that have been involved in both cloud and on-premise implementations what the key differences were. The most common answers are the amount of support and financial investment needed.
Lower on the list were actual system differences like infrastructure or performance. This suggests that skills needed from external sources may be somewhat interchangeable, and you don’t necessarily have to look for someone with experience in your preferred environment.
While some are enticed by the lower cost, limited timeline, and unified process of a single-phase or “big bang” approach, consultants tell us that their customers chose a phased rollout five times as often.
Risk aversion and the ability to learn from previous phases appear to be more important than cost or timing. Is there a best practice in terms of number of phases? According to our data, 58% of consultants say the most common number of phases is three to five.
Another consideration not discussed enough as part of an S/4HANA migration is the certification status of third-party application providers. Only 15% of consultants believe that customers give an appropriate amount of discussion and evaluation of third-party certification, and an equal amount say that their customers aren’t even discussing. Nearly all agree that more time should be spent talking about the implications of certification and subsequent potential changes to business processes. If these integrations fail, the mid-stream downtime could cost an organization millions of dollars and have an impact on customer experience. You can’t afford to overlook this.
Most consultants believe customers are not wildly out of balance with their project scoping of the S/4HANA transition. Almost three-fourths (72%) say their customers accurately assess the scope of the S/4HANA project most or some of the time. When customers aren’t completely aware of the proper scope needed, the most common gaps are lack of experienced personnel and data that has not been cleaned. Cost, timing,and testing, while still important, are secondary concerns.
Another consideration not discussed enough as part of an S/4HANA migration is the certification status of third-party applications. Only 15% of consultants believe that customers spend an appropriate amount of time discussing and evaluating third-party certification.
If these integrations fail, the mid-stream downtime could cost an organization millions of dollars and have an impact on customer experience. You can’t afford to overlook this.
Almost three quarters (72%) of organizations are at least somewhat accurate when assessing the scope of their projects.
When customers aren’t completely aware of the proper scope needed, the most common gaps are lack of experienced personnel and data that has not been cleaned. Cost, timing, and testing, while still important, are secondary concerns.
Still, consultants identify scope creep as the biggest factor in missed go-live dates (76%), suggesting that although some get this right, getting it wrong could cost companies millions of dollars.